Paragraph 11 Removal etc of the Authority’s moorings and buoysI1

England and Wales

(1)

Subject to paragraph 11(2), if by reason of the construction of any tidal work it is reasonably necessary for the Authority to incur the cost of—

(a)

temporarily or permanently altering, removing, re-siting, repositioning or reinstating existing moorings or aids to navigation (including navigation marks or lights) owned by the Authority;

(b)

laying down and removing substituted moorings or buoys; or

(c)

carrying out dredging operations for any such purpose;

not being costs which it would have incurred for any other reason, the undertaker shall pay the costs reasonably so incurred by the Authority.

(2)

The Authority shall give to the undertaker not less than 20 business days’ notice of its intention to incur such costs, and take into account any representations which the undertaker may make in response to the notice within 10 business days of the receipt of the notice.

Annotations

Commencement

I1

Sch. 16 Pt. 2 para. 11 in force at 24.9.2014, see art. 1