Paragraph 17 Scour monitoring and mitigationI1
England and Wales
The undertaker shall submit a scour and accretion monitoring and mitigation strategy to the Authority for approval, such determination to be given—
by 30th September 2014; or
within 5 business days of this Order coming into force; or
by the expiry of 20 business days from receipt of the submission made under this paragraph,
whichever is the latest.
Prior to the commencement of any tidal work, a scour and accretion monitoring and mitigation plan for that tidal work shall be prepared by the undertaker in accordance with the scour and accretion monitoring and mitigation strategy approved under paragraph 17(1) or otherwise determined, and the scour and accretion monitoring and mitigation plan shall be submitted to the Authority for approval within 35 business days of the specified day.
Following any submission of a scour and accretion monitoring and mitigation plan under paragraph 17(2), the approval process in paragraph 5 shall apply to such submission as if it were a submission under paragraph 5(1) and the “specified day” shall be the first business day on which such submission is received by the Authority under paragraph 17(2).
The carrying out of any tidal work shall proceed only in accordance with the scour and accretion monitoring and mitigation plan as approved by the Authority under paragraph 17(2).
Annotations
Commencement
- I1
Sch. 16 Pt. 2 para. 17 in force at 24.9.2014, see art. 1