Paragraph 7 General provision as to construction of works including inspectionI1
England and Wales
The construction or carrying out of any tidal work shall, once commenced, be carried out by the undertaker with all reasonable dispatch and to the reasonable satisfaction of the Authority so that river traffic, the flow or regime of the river and the exercise of the Authority’s functions shall not suffer more interference than is reasonably practicable, and the Authority shall be entitled by its officer at all reasonable times, on giving such notice as may be reasonable in the circumstances, to inspect and survey such operations.
Annotations
Commencement
- I1
Sch. 16 Pt. 2 para. 7 in force at 24.9.2014, see art. 1