OpenLegislation

Paragraph 4 Detailed design approvalI1

England, Wales and Scotland

(1)

No stage of the authorised development below must commence until details of the layout, scale and external appearance of that stage have been submitted to and approved in writing by the relevant planning authority—

(a)

Work No. 4;

(b)

Work No. 5;

(c)

Work No. 6;

(d)

Work No. 7;

(e)

the detailed alignment of the pipeline works; and

(f)

the working width and temporary compounds.

(2)

The works approved by the relevant planning authority under sub-paragraph (1) must be in accordance with the works plan (or relevant parts of the plan) and be within the Order limits.

(3)

The authorised development must be carried out in accordance with the approved details.

Annotations

Commencement

I1

Sch. 1 Pt. 2 para. 4 in force at 25.3.2016, see art. 1