Paragraph 9 Provision of landscaping at the AGI siteI1
England, Wales and Scotland
The construction of the AGI site must not commence until a written landscaping scheme in relation to those works has been submitted to and approved in writing by the relevant planning authority. The landscaping scheme must include details of all proposed hard and soft landscaping works, including—
cultivation, importing of materials and other operations to ensure plant establishment;
proposed finished ground levels;
hard surfacing materials;
vehicular and pedestrian access, parking and circulation areas;
minor structures such as furniture, refuse or other storage units, signs and lighting;
proposed and existing functional services above and below ground including drainage, power and communications cables and pipelines, manholes and supports;
details of existing trees to be retained with measures for their protection during the construction period;
implementation timetables for all landscaping works; and
future maintenance regimes.
All landscaping works must be carried out in accordance with the landscaping scheme and the implementation timetables approved under sub-paragraph (1).
Annotations
Commencement
- I1
Sch. 1 Pt. 2 para. 9 in force at 25.3.2016, see art. 1