The Tillbridge Solar Order 2025f1(“the Tillbridge Order”), which granted development consent within the meaning of the Planning Act 2008f2 (“the Act”) contains correctable errors within the meaning of paragraph 1 of Schedule 4 to the Act.
In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant periodf3, the Secretary of State received a written request from the applicantf4 for the correction of errors and omissions in the Tillbridge Order.
In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed each relevant local planning authorityf5 for the area in which the land to which the Tillbridge Order relates is situated that the request has been received.
The Secretary of State, in exercise of the powers conferred by paragraphs 1(4) and 1(8) of Schedule 4 to the Act, makes the following Order.
Annotations
Footnotes
- f1
- f2
-
2008 c. 29. Paragraph 1 of Schedule 4 to the Act was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20). There are other amendments to the Act which are not relevant to this Order.
- f3
-
The relevant period is defined in paragraph 1(6)(a) of Schedule 4 to the Act.
- f4
-
The term “applicant” is defined in paragraph 4 of Schedule 4 to the Act.
- f5
-
As defined in paragraph 4 of Schedule 4 to the Act.