Regulation 44 Determination of conditions

England and Wales

(1)

A relevant mineral planning authority must give written notification of its determination of an EIA application within 16 weeks of the latest of the following dates—

(a)

the date falling 21 days after the date on which the documents required by regulation 21 are received by it or, if those documents are received on different dates, the date falling 21 days after the date on which the final document is received;

(b)

the date falling 21 days after the date on which any documents required by regulation 31 are received by it or, if those documents are received on different dates, the date falling 21 days after the date on which the final document is received;

(c)

the date falling 21 days after the date on which the relevant mineral planning authority publishes any other relevant information under regulation 37,

or such longer period as may be agreed between the applicant and the relevant mineral planning authority.

(2)

The Welsh Ministers must give written notification of their determination of an EIA application within such period following the latest of the following dates as they may reasonably require—

(a)

the date falling 21 days after the date on which the documents required by regulation 21 are received by them or, if those documents are received on different dates, the date falling 21 days after the date on which the final document is received;

(b)

the date falling 21 days after the date on which any documents required by regulation 31 are received by them or, if those documents are received on different dates, the date falling 21 days after the date on which the final document is received;

(c)

the date falling 21 days after the date on which the Welsh Ministers publish any other relevant information under regulation 37,

or such longer period as may be agreed between the Welsh Ministers and the applicant or appellant.