Regulation 42 Interpretation of this Part
England and Wales
In this Part—
“enforcement functions” (“swyddogaethau gorfodi”) means—
- (a)
the issue of an enforcement notice under section 172 of the 1990 Act (issue of enforcement notice) M1;
- (b)
the issue of a planning contravention notice under section 171C of the 1990 Act (power to require information about activities on land) M2;
- (c)
the issue of a temporary stop notice under section 171E of the 1990 Act (temporary stop notice) M3;
- (d)
the issue of a stop notice under section 183 of the 1990 Act (stop notices) M4;
- (e)
- (f)
an application to the court for an injunction under section 187B of the 1990 Act (injunctions restraining breaches of planning control) M6;
- (g)
F2the exercise of the power to enter land under section 106 of the 2024 Act (powers to enter land for enforcement purposes);
- (h)
the serving of an information notice under section 111 of the 2024 Act (power to require information);
- (i)
the giving of a notice of unauthorised development under section 113 of the 2024 Act (notice of unauthorised development);
- (j)
the issue of a temporary stop notice under section 117 of the 2024 Act (power to issue a temporary stop notice); and
- (k)
an application to the court for an injunction under section 122 of the 2024 Act (injunction to restrain prohibited activity);
- (a)
“ground (a) appeal” (“apêl sail (a)”) means an appeal brought under section 174(2)(a) of the 1990 Act (appeal against enforcement notice) M7; and
“unauthorised EIA development” (“datblygiad AEA anawdurdodedig”) means EIA development which is the subject of an enforcement notice under section 172 of the 1990 Act (issue of enforcement notice) F3or a notice of unauthorised development under section 113 of the 2024 Act.
Annotations
Textual amendments
- F1
Word in reg. 42 omitted (15.12.2025) by virtue of The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(38)(a)(i) (with reg. 12(44))
- F2
Words in reg. 42 inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(38)(a)(ii) (with reg. 12(44))
- F3
Words in reg. 42 inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(38)(b) (with reg. 12(44))
Marginal citations
- M1
Section 172 was substituted by section 5 of the 1991 Act.
- M2
Section 171C was inserted by section 1 of the 1991 Act and amended by article 5(a) of S.I. 2004/3156 (W. 273).
- M3
Section 171E was inserted by section 52 of the Planning and Compulsory Purchase Act 2004 (c. 5).
- M4
Section 183 was substituted by section 9 of the 1991 Act.
- M5
Section 187A was inserted by section 2 of the 1991 Act. There is a further amendment which is not relevant to Wales.
- M6
Section 187B was inserted by section 3 of the 1991 Act.
- M7
Section 174 was amended by sections 6, 32 and 84 of, and paragraph 22 of Part 1 to Schedule 19 to the 1991 Act, S.I. 2004/3156 (W. 273), section 63 of, and paragraphs 2 and 5 of Schedule 17 to the Enterprise and Regulatory Reform Act 2013 (c. 24) and by section 46 of the Planning (Wales) Act 2015 (anaw 4). There are other amendments which are not relevant to Wales. See also section 177(5) which was amended by paragraph 24 of Schedule 7 to the 1991 Act.