OpenLegislation

Paragraph 4 I1

England and Wales

(1)

This paragraph applies where—

(a)

an application is made for approval of one or more reserved matters (“the current application”); and

(b)

the applicant has previously applied for such approval under the same outline planning permission and paid fees in relation to one or more such applications; and

(c)

no application has been made under that permission other than by or on behalf of the applicant.

(2)

Where the amount paid as mentioned in sub-paragraph (1)(b) is not less than the amount which would be payable if the applicant were, by the current application, seeking approval of all the matters reserved by the outline permission (and in relation to the whole of the development authorised by the permission), the fee payable in respect of the current application is F1the amount published by the Welsh Ministers in accordance with regulation 2ZA (publication of fee document).

(3)

Where—

(a)

a fee has been paid as mentioned in sub-paragraph (1)(b) at a rate lower than that prevailing at the date of the current application; and

(b)

sub-paragraph (2) would apply if that fee had been paid at the rate applying at that date,

the fee in respect of the current application is F2the amount published by the Welsh Ministers in accordance with regulation 2ZA (publication of fee document).

Annotations

Textual amendments

F1

Words in Sch. 1 para. 4(2) substituted (20.10.2025) by The Town and Country Planning (Fees for Applications, Deemed Applications and Site Visits) (Wales) (Amendment) Regulations 2025 (S.I. 2025/1095), regs. 1(2), 3(9)(b) (with reg. 5)

F2

Words in Sch. 1 para. 4(3) substituted (20.10.2025) by The Town and Country Planning (Fees for Applications, Deemed Applications and Site Visits) (Wales) (Amendment) Regulations 2025 (S.I. 2025/1095), regs. 1(2), 3(9)(c) (with reg. 5)

Commencement

I1

Sch. 1 para. 4 in force at 1.10.2015, see reg. 1(1)