Paragraph CB.3 Interpretation of Class CBF1

England and Wales

For the purposes of Class CB—

  • “published admission number” has the meaning given in paragraph M.3 of Part 7 of this Schedule;

  • “RAAC” means reinforced autoclaved aerated concrete;

  • “RAAC-affected building” means a building on school land which has been vacated, in whole or in part, pursuant to a decision by the school, in discharge of its health and safety obligations, that the building should be vacated due to the presence of RAAC;

  • “relevant time” means—

    1. (a)

      where development begins after 25th October 2023, before development begins or as soon as reasonably practicable after it has begun;

    2. (b)

      where development begins on or before 25th October 2023, as soon as reasonably practicable after that date;

  • “school” does not include buildings or land provided at any time under Class C or CA;

  • “school land” means land available for use by a school for a purpose falling within Class F.1(a) (provision of education) of Schedule 2 to the Use Classes Order.

Annotations

Textual amendments

F1

Sch. 2 Pt. 4 Class CB inserted (25.10.2023) by The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2023 (S.I. 2023/1110), arts. 1(1), 2