Paragraph A.1 Development not permitted

F1Development not permitted: block of flats

(1)

Development is not permitted by Class A on a block of flats, or a building within the curtilage of a block of flats, if—

(a)

the solar PV or solar thermal equipment would protrude more than 0.2 metres beyond the plane of the wall or F2, in the case of a pitched roof, the roof slope when measured from the perpendicular with the external surface of the wall or F3pitched roof slope;

(b)

F4in the case of solar PV or solar thermal equipment on a pitched roof, it would result in the highest part of the solar PV or solar thermal equipment being higher than the highest part of the roof (excluding any chimney);

F5(ba)

in the case of solar PV or solar thermal equipment on a flat roof, it would result in the highest part of the solar PV or solar thermal equipment being more than 0.6 metres higher than the highest part of the roof (excluding any chimney);

(c)

in the case of land within a conservation area or which is a World Heritage Site, the solar PV or solar thermal equipment would be installed on a wall which fronts a highway;

(d)

the solar PV or solar thermal equipment would be installed on a site designated as a scheduled monument; F6...

F7(e)

the solar PV or solar thermal equipment would be installed on a block of flats, or on a building within the curtilage of a block of flats, if the block of flats is a listed building; or

F8(f)

in the case of plug-in solar, where any part of the plug-in solar would be installed on a wooden wall, balcony or enclosure or on any part of the exterior of a block of flats which is clad in timber.

F9Development not permitted: dwellinghouse

(2)

Development is not permitted by Class A on a dwellinghouse, or a building within the curtilage of a dwellinghouse, if—

(a)

in the case of solar PV or solar thermal equipment on a wall, it would result in—

(i)

where the wall abuts on a highway, the solar PV or solar thermal equipment protruding more than 0.2 metres beyond the plane of the wall when measured from the perpendicular with the external surface of that wall; or

(ii)

in any other case, the solar PV or solar thermal equipment protruding more than 0.4 metres beyond the plane of the wall when measured from the perpendicular with the external surface of that wall;

(b)

in the case of solar PV or solar thermal equipment on a balcony enclosure or roof enclosure, it would result in—

(i)

where the enclosure abuts on a highway, the solar PV or solar thermal equipment protruding more than 0.2 metres beyond the enclosure when measured from the perpendicular with the external surface of that enclosure; or

(ii)

in any other case, the solar PV or solar thermal equipment protruding more than 0.4 metres beyond the enclosure when measured from the perpendicular with the external surface of that enclosure;

(c)

in the case of solar PV or solar thermal equipment on a pitched roof, it would result in either or both of—

(i)

the solar PV or solar thermal equipment protruding more than 0.2 metres beyond the roof slope when measured from the perpendicular with the external surface of the pitched roof slope;

(ii)

the highest part of the solar PV or solar thermal equipment being higher than the highest part of the roof (excluding any chimney);

(d)

in the case of solar PV or solar thermal equipment on a flat roof, it would result in the highest part of the solar PV or solar thermal equipment being more than 0.6 metres higher than the highest part of the roof (excluding any chimney);

(e)

in the case of land within a conservation area or which is a World Heritage Site, the solar PV or solar thermal equipment would be installed on a wall, balcony or roof enclosure which fronts a highway;

(f)

the solar PV or solar thermal equipment would be installed on a site designated as a scheduled monument;

(g)

the solar PV or solar thermal equipment would be installed on a dwellinghouse, or on a building within the curtilage of a dwellinghouse, if the dwellinghouse is a listed building; or

(h)

in the case of plug-in solar, where any part of the plug-in solar would be installed on a wooden wall, balcony or enclosure or on any part of the exterior of a dwellinghouse where that part is clad in timber.

Annotations

Textual amendments

F1

Words in Sch. 2 Pt. 14 Class A para. A.1 substituted (27.8.2026) by The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026 (S.I. 2026/896), arts. 1(2), 3(a) (with art. 6)

F2

Words in Sch. 2 Pt. 14 para. A.1(a) inserted (21.12.2023) by The Town and Country Planning (General Permitted Development etc.) (England) (Amendment) (No. 2) Order 2023 (S.I. 2023/1279), arts. 1(1), 4(2)(a)(i)

F3

Word in Sch. 2 Pt. 14 para. A.1(a) inserted (21.12.2023) by The Town and Country Planning (General Permitted Development etc.) (England) (Amendment) (No. 2) Order 2023 (S.I. 2023/1279), arts. 1(1), 4(2)(a)(ii)

F4

Words in Sch. 2 Pt. 14 para. A.1(b) inserted (21.12.2023) by The Town and Country Planning (General Permitted Development etc.) (England) (Amendment) (No. 2) Order 2023 (S.I. 2023/1279), arts. 1(1), 4(2)(b)

F5

Sch. 2 Pt. 14 para. A.1(ba) inserted (21.12.2023) by The Town and Country Planning (General Permitted Development etc.) (England) (Amendment) (No. 2) Order 2023 (S.I. 2023/1279), arts. 1(1), 4(2)(c)

F6

Word in Sch. 2 Pt. 14 Class A para. A.1(1)(d) omitted (27.8.2026) by virtue of The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026 (S.I. 2026/896), arts. 1(2), 3(b) (with art. 6)

F7

Sch. 2 Pt. 14 Class A para. A.1(1)(e) substituted (27.8.2026) by The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026 (S.I. 2026/896), arts. 1(2), 3(c) (with art. 6)

F8

Sch. 2 Pt. 14 Class A para. A.1(1)(f) inserted (27.8.2026) by The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026 (S.I. 2026/896), arts. 1(2), 3(d) (with art. 6)

F9

Sch. 2 Pt. 14 Class A para. A.1(2) inserted (27.8.2026) by The Town and Country Planning (General Permitted Development) (England) (Amendment) Order 2026 (S.I. 2026/896), arts. 1(2), 3(e) (with art. 6)