Paragraph C Permitted developmentF1F2
Development carried out by or on behalf of the Crown on operational Crown land for operational purposes consisting of—
the installation of additional or replacement plant or machinery;
the provision, rearrangement or replacement of a sewer, main, pipe, cable or other apparatus; or
the provision, rearrangement or replacement of a private way, private railway, siding or conveyor.
Annotations
Textual amendments
- F1
Order revoked (E.) (15.4.2015) by The Town and Country Planning (General Permitted Development) (England) Order 2015 (S.I. 2015/596), art. 1(1), Sch. 4 para. 1 (with arts. 1(2), 8(2)(3))
- F2
Sch. 2 Pts. 34-38 inserted (W.) (7.6.2006) byThe Town and Country Planning (Miscellaneous Amendments and Modifications relating to Crown Land) (Wales) Order 2006 (S.I. 2006/1386), arts. 1(1), 3(6)(a), Sch. Pt. 2