Paragraph C.1 Development not permittedF1F2
Development is not permitted by Class C if—
in the case of the installation of a ground source heat pump, it would result in the presence within the curtilage of more than one ground source heat pump;
the total area covered by the excavation to accommodate the ground source heat pump (including any pipes) exceeds 0.5 hectares;
the ground source heat pump would be installed within the curtilage of a listed building; F3...
the ground source heat pump would be installed on a site designated as a scheduled monument F4; or
the capacity of the ground source heat pump exceeds 45 kilowatts thermal.
Annotations
Textual amendments
- F1
Order revoked (E.) (15.4.2015) by The Town and Country Planning (General Permitted Development) (England) Order 2015 (S.I. 2015/596), art. 1(1), Sch. 4 para. 1 (with arts. 1(2), 8(2)(3))
- F2
Sch. 2 Pt. 43 inserted (W.) (5.10.2012) by The Town and Country Planning (General Permitted Development) (Amendment) (Wales) (No. 2) Order 2012 (S.I. 2012/2318), arts. 1(1), 4, Sch.
- F3
Word in Sch. 2 Pt. 43 Class C para. C.1(c) omitted (W.) (1.4.2019) by virtue of The Town and Country Planning (General Permitted Development) (Amendment) (Wales) Order 2019 (S.I. 2019/330), arts. 1(2), 7(7)
- F4
Sch. 2 Pt. 43 Class C para. C.1(e) and word inserted (W.) (1.4.2019) by The Town and Country Planning (General Permitted Development) (Amendment) (Wales) Order 2019 (S.I. 2019/330), arts. 1(2), 7(7)
Notes on Part 43
Textual amendments
- F3
Sch. 2 Pt. 43 heading substituted (W.) (1.4.2019) by The Town and Country Planning (General Permitted Development) (Amendment) (Wales) Order 2019 (S.I. 2019/330), arts. 1(2), 7(2)