Part 16 DEVELOPMENT ANCILLARY TO MINING OPERATIONSI1

Scotland

For the purposes of Part 16—

  • “active access” means a surface access to underground workings which is in normal and regular use for the transportation of minerals, materials, spoil or men;

  • “ancillary mining land” means land adjacent to and occupied together with a mine at which the winning and working of minerals is carried out in pursuance of planning permission granted or deemed to be granted under Part III of the Act;

  • “approved site” is an area of land—

    1. (a)

      identified in a grant of planning permission or any instrument by virtue of which planning permission is deemed to be granted, as land which may be used for development described in this class; or

    2. (b)

      in any other case, it is land immediately adjoining an active access to an underground mine which, on the date of coming into force of this Order, was in use for the purposes of that mine, in connection with the purposes described in sub-paragraph (2)(b)(i) or (ii) of Class 55 or sub-paragraph (2)(b)(i) to (iii) of Class 56;

  • “normal and regular use” means, for the purpose of the definition of “active access” use other than use in the course of intermittent visits carried out for the purpose of inspection and maintenance of the fabric of the mine or of any plant or machinery;

  • “prior approval of the planning authority” means prior written approval of that authority of detailed proposals for the siting, design and external appearance of the proposed building, plant or machinery as erected, installed, extended or altered;

  • “underground mine” is a mine at which minerals are worked principally by underground methods.

  1. 55Paragraph 55
  2. 56Paragraph 56
  3. 57Paragraph 57

Annotations

Commencement

I1

Sch. 1 Pt. 16 in force at 13.3.1992, see art. 1(4)