Regulation 41 Review of LDPI1F1
England and Wales
For the purposes of section 69(1), the LPA must commence a review of its LDP at intervals not longer than every four years from the later of—
the date of the first adoption of the LDP; or
the date of the last adoption of the LDP following a review under section 69(1).
Before it prepares a revision of an LDP, an LPA must review its LDP.
For the purposes of paragraph (2), such a review may be either a review under section 69(1) or a selective review.
The LPA must report to the Welsh Ministers on the findings of a selective review.
An LPA must approve by resolution a report of a review prepared in accordance with section 69(1) before it submits it to the Welsh Minsters in accordance with section 69(2).
An LPA must approve by resolution a report of a selective review and submit the approved report to the Welsh Minsters.
As soon as reasonably practicable after a review report has been approved by resolution of the LPA in accordance with paragraph (5) or (6), the LPA must—
publish the review report on its website; and
make copies available at its principal office and at other places that the LPA considers appropriate.
For the purposes of this regulation “selective review” means a review of part or parts of an LDP.
Annotations
Textual amendments
- F1
Reg. 41 substituted (28.8.2015) by The Town and Country Planning (Local Development Plan) (Wales) (Amendment) Regulations 2015 (S.I. 2015/1598), regs. 1(1), 2(29) (with reg. 3)
Commencement
- I1
Reg. 41 in force at 15.10.2005, see reg. 1(1)