OpenLegislation

Regulation 7 Determination of applicationI1

Scotland

(1)

F1The planning authority are to give notice of their determination to an applicant under section 75A(5) of the Act within the period of two months after the date on which the application is taken to have been made in accordance with regulation 4.

(2)

The planning authority must when giving notice of their determination to the applicant send a copy of that notice to every interested party.

F2(3)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Annotations

Textual amendments

F1

Word in reg. 7(1) substituted (14.9.2015) by The Town and Country Planning (Miscellaneous Amendments) (Scotland) Regulations 2015 (S.S.I. 2015/249), regs. 1, 3(2)(a)

F2

Reg. 7(3) omitted (14.9.2015) by virtue of The Town and Country Planning (Miscellaneous Amendments) (Scotland) Regulations 2015 (S.S.I. 2015/249), regs. 1, 3(2)(b)

Commencement

I1

Reg. 7 in force at 1.2.2011, see reg. 1(1)