The Town and Country Planning (Power to Override Easements and Applications by Statutory Undertakers) (Wales) Order 2015 in Scotland
W.S.I. 2015/1794 · Made 13 October 2015
Town And Country Planning, Wales
Made 13 October 2015
Coming into force in accordance with article 1(2)
The Welsh Ministers, in exercise of the powers conferred by section 203 of the Planning Act 2008f1, make the following Order:
In accordance with section 203(9) of that Act a draft of this Order was laid before and approved by a resolution of the National Assembly for Wales.
Annotations to the whole text
Footnotes
- f1
Contents
- 1Title, commencement and interpretation
- 2Power to override easements and other rights
- 3Power to override easements and other rights
- 4Power to override easements and other rights
- 5Power to override easements and other rights
- 6Applications for planning permission by statutory undertakers
- 7Transitional provision
- Signature
- Explanatory note
1Title, commencement and interpretation
The title of this Order is The Town and Country Planning (Power to Override Easements and Applications by Statutory Undertakers) (Wales) Order 2015.
This Order comes into force on the day after the day on which it is made.
In this Order “the 1990 Act” (“Deddf 1990”) means the Town and Country Planning Act 1990f1.
2Power to override easements and other rights
In paragraph 6(1A) of Schedule 28 to the Local Government, Planning and Land Act 1980f1 after “in England” insert “or Wales”.
3Power to override easements and other rights
In section 19(1A) of the New Towns Act 1981f1 omit “in England”.
4Power to override easements and other rights
In paragraph 5(1A) of Schedule 10 to the Housing Act 1988f1 after “in England” insert “or Wales”.
5Power to override easements and other rights
In section 237(1A) of the 1990 Actf1 omit “in England”.
6Applications for planning permission by statutory undertakers
In section 266 of the 1990 Actf1 after subsection (1A) insert—
“(1B)Subsection (1) has effect in relation to an application or appeal relating to land in Wales only if the Welsh Ministers or the appropriate Minister have given a direction for it to have effect in relation to the application or appeal (and the direction has not been revoked).”
7Transitional provision
The amendment made by article 6 applies only in relation to applications and appeals made on or after the day on which this Order comes into force.
Signature
Carl Sargeant
Minister for Natural Resources, one of the Welsh Ministers
13 October 2015
Explanatory note
(This note is not part of the Order)
This Order confers powers on local authorities and other bodies to override easements and other rights which would otherwise restrict their use of land that has been acquired or appropriated for planning purposes. They can do this only if the use is in accordance with planning permission. It makes provision in relation to Wales which corresponds to section 194(1) of, and Schedule 9 to, the Planning Act 2008 (“the 2008 Act”).
This Order also disapplies the requirement for the Welsh Ministers and the appropriate Minister to decide jointly certain planning applications and appeals where the application has been made by a statutory undertaker. The Welsh Ministers or the appropriate Minister may however direct that the requirement for joint decisions continues to apply in relation to the relevant application or appeal. The Order makes provision in relation to Wales which corresponds to section 195 of the 2008 Act.
Article 7 makes transitional provision. It provides that section 266(1B) of the Town and Country Planning Act 1990 applies where an application or appeal is made after the Order comes into force.
The Welsh Ministers’ Code of Practice on the carrying out of Regulatory Impact Assessments was considered in relation to this Order. As a result, it was not considered necessary to carry out a regulatory impact assessment as to the likely costs and benefits of complying with this Order.