Article 42 Consultation with designated planning authorityF1
Subject to paragraph (2), the Secretary of State must, before determining a connected listed building application—
notify the designated planning authority giving a period of at least 21 days, beginning no earlier than the date the Secretary of State sends the notice under article 35(2) in relation to the application, within which to make representations about the application (including as to the manner in which the application is to be determined); and
take into account any such representations received.
Paragraph (1)(a) does not apply if before the end of the period referred to in that paragraph the Secretary of State has received a substantive response (within the meaning of article 41(5)) concerning the application from the designated planning authority.