OpenLegislation

Article 48 Detrimental effect of mobile homes on the amenity of the site applications

(1)

This rule applies if a site owner applies for a determination under paragraph 5A(2)(a) of Chapter 2, or paragraph 6(1)(a) of Chapter 4, of Part 1 of Schedule 1 to the 1983 Act that, having regard to its condition, the mobile home is having a detrimental effect on the amenity of the site.

(2)

If, at a hearing, it appears to the Tribunal that the mobile home is having a detrimental effect on the amenity of the site, but that if certain repairs to the mobile home were carried out, the mobile home would cease to have such a detrimental effect, it must—

(a)

inform the site owner and the occupier of the repairs which should be carried out;

(b)

invite both the occupier of the mobile home and the site owner to provide information in relation to those repairs as to—

(i)

the time needed to carry them out; and

(ii)

the cost of carrying them out; and

(c)

invite the occupier of the mobile home to indicate whether or not the occupier would be willing to carry out those repairs.

(3)

The Tribunal, having regard to information given under paragraph (2)(b) and (c) must either—

(a)

make a determination under paragraph 5A(2)(a) of Chapter 2, or paragraph 6(1)(a) of Chapter 4, of Part 1 of Schedule 1 to the 1983 Act; or

(b)

if paragraph 5A(4) of Chapter 2, or paragraph 6(2) of Chapter 4, of Part 1 of that Schedule applies, make an interim order requiring the occupier of the mobile home to carry out such repairs within such time as the Tribunal considers reasonable.

(4)

Upon making an interim order under paragraph (3)(b), the Tribunal must adjourn the hearing and set a further hearing date for within 7 days from the date by which the specified repairs must be carried out.

(5)

The Tribunal must request each of the site owner and the occupier to state, no later than 4 days before the date of the further hearing, whether (in their opinion) the specified repairs have been completed.

(6)

When setting a further hearing date under paragraph (4), the Tribunal must—

(a)

give the parties not less than 14 days' notice of the hearing date; and

(b)

invite both the site owner and the occupier to indicate, no later than 4 days before the date of the hearing, whether in their opinion the repairs described in the order have been completed.

(7)

At the further hearing—

(a)

if the Tribunal has received notification from each of the occupier and the site owner that the repairs ordered under paragraph (3)(b) have been completed, it must dismiss the application;

(b)

if the Tribunal has not received such notification it must request the parties present to make representations as to the extent of repairs left to be carried out and the time needed to carry them out; and

(c)

having considered any such representations, it must either make a further interim order under paragraph (3)(b) or make a determination under paragraph 5A(2)(a) of Chapter 2, or paragraph 6(1)(a) of Chapter 4, of Part 1 of Schedule 1 to the 1983 Act.

(8)

If, before the date of the further hearing, the Tribunal is satisfied that the repairs have been completed, the Tribunal may dispense with the need for a further hearing and may dismiss the application.