Paragraph 19 Construction trafficI1
England, Wales and Scotland
No stage of the onshore works may be commenced until for that stage, after consultation with the highway authority, a construction traffic management plan in accordance with the outline traffic management plan including a contractor travel plan has been submitted to and approved by the relevant planning authority.
Construction and contractor traffic related to the authorised development must use only Work No. 48 or 49 to access Work Nos. 50 to 55.
The timings for the construction of Work Nos. 48 and 49 must be included within the construction method statement approved as part of the relevant code of construction practice.
The construction traffic management plan and contractor travel plan must be implemented as approved.