Paragraph 9 Fencing and other means of enclosureI1
England, Wales and Scotland
No stage of the onshore works may be commenced until for that stage written details of all proposed fences, walls or other means of enclosure have been submitted to and approved by the relevant planning authority.
All temporary construction compounds must remain securely fenced in accordance with the approved details at all times during construction of the onshore works.
Temporary fencing, except temporary fencing for the beach works, must be removed on completion of the relevant stage of the onshore works.
Temporary fencing for the beach works must be removed on completion of construction of those works excluding testing.
Any approved permanent fencing in relation to Work Nos. 9A and 50A must be completed before the relevant Work is brought into use and maintained for the operational lifetime of Work Nos. 9A and 50A.
In this Requirement, “beach works” means Work No. 2 and works related to the installation of cable ducts and cable circuits within Work No. 3 but excluding Work Nos. 3A and 3B.
Annotations
Commencement
- I1
Sch. 1 para. 9 in force at 27.9.2016, see art. 1(2)