Paragraph 5 I1

England, Wales and Scotland

Except in an emergency, the alteration, extension, removal or relocation of any apparatus must not be implemented until—

(a)

any requirement for permits under F1the Environmental Permitting (England and Wales) Regulations 2016 or other legislation and any other associated consents are obtained, and any approval or agreement required from Anglian Water on alternative outfall locations as a result of such relocation are approved, such approvals from Anglian Water not to be unreasonably withheld or delayed; and

(b)

the undertaker has made the appropriate application required under the Water Industry Act 1991 together with a plan and section of the works proposed and Anglian Water has agreed all of the contractual documentation required under the Water Industry Act 1991, such agreement not to be unreasonably withheld or delayed,

and the works must be executed only in accordance with the plan and description submitted and with such reasonable requirements as may be made by Anglian Water for the alteration or otherwise for the protection of the apparatus or for securing access to it.

Annotations

Textual amendments

F1

Words in Sch. 8 Pt. 4 para. 5(a) substituted (1.1.2017) by The Environmental Permitting (England and Wales) Regulations 2016 (S.I. 2016/1154), reg. 1(1), Sch. 29 para. 121(4) (with regs. 1(3), 77-79, Sch. 4)

Commencement

I1

Sch. 8 Pt. 4 para. 5 in force at 27.9.2016, see art. 1(2)