The Network Rail (Norton Bridge Area Improvements) Order 2014

S.I. 2014/909 · Made 31 March 2014 · Extends to England, Wales and Scotland

Up to date with all changes known to legislation.gov.uk, revised to 28 December 2017.

Infrastructure Planning

Made 31st March 2014

Coming into force 21st April 2014

An application has been made to the Secretary of State, in accordance with the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009f1, for an order under sections 37, 114, 115, 117(4), 120 and 122 of the Planning Act 2008f2.

The application was examined in accordance with Chapter 4 of Part 6 of the 2008 Act, and the Infrastructure Planning (Examination Procedure) Rules 2010f3, by a single appointed person appointed by the Secretary of State in accordance with Chapter 3 of Part 6 of the 2008 Act.

The single appointed person, having considered the representations made and not withdrawn and the application together with accompanying documents, in accordance with section 83 of the 2008 Act, has submitted a report to the Secretary of State.

The Secretary of State, having considered the representations made and not withdrawn, and the report of the single appointed person, has decided to make an Order granting development consent for the development described in the application and consent for ancillary works with modifications which in the opinion of the Secretary of State do not make any substantial change to the proposals comprised in the application.

The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and 122 of, and paragraphs 1 to 3, 10 to 17, 24, 26, 36 and 37 of Part 1 of Schedule 5 to, the 2008 Act, makes the following Order—

Annotations to the whole text

Footnotes

f1

S.I. 2009/2264, amended by S.I. 2010/439, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/722, S.I. 2013/755.

f2

2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20).

f3

S.I. 2010/103.

Contents

  1. Part 1: Preliminary
  2. 1Citation and commencement
  3. 2Interpretation
  4. 3Incorporation of the Railways Clauses Acts
  5. Part 2: Principal Powers
  6. 4Development consent etc. granted by the Order
  7. 5Maintenance of authorised development
  8. 6Limits of deviation
  9. 7Benefit of Order
  10. Part 3: Streets
  11. 8Power to alter layout etc. of streets
  12. 9Street works
  13. 10Construction and maintenance of new or altered streets
  14. 11Stopping up of streets
  15. 12Application of the 1991 Act
  16. 13Temporary stopping up of streets
  17. 14Access to works
  18. 15Agreements with street authorities
  19. 16Construction of bridges and tunnels
  20. 17Level crossing
  21. Part 4: Supplemental powers
  22. 18Discharge of water
  23. 19Authority to survey and investigate the land
  24. Part 5: Powers of acquisition
  25. 20Compulsory acquisition of land
  26. 21Time limit for exercise of authority to acquire land compulsorily
  27. 22Compulsory acquisition of rights
  28. 23Private rights
  29. 24Application of the Compulsory Purchase (Vesting Declarations) Act 1981
  30. 25Acquisition of subsoil or airspace only
  31. 26Acquisition of part of certain properties
  32. 27Rights under or over streets
  33. 28Temporary use of land by Network Rail
  34. 29Temporary use of land by National Grid
  35. 30Temporary use of land for maintaining authorised development
  36. 31Statutory undertakers
  37. 32Apparatus and rights of statutory undertakers in stopped up streets
  38. 33Recovery of costs of new connections
  39. Part 6: Operations
  40. 34Operation and use of railways
  41. 35Felling or lopping of trees
  42. Part 7: Miscellaneous and general
  43. 36Operational land for purposes of the 1990 Act
  44. 37Defence to proceedings in respect of statutory nuisance
  45. 38Traffic regulation
  46. 39Protections of interests
  47. 40Application of the 1973 Act
  48. 41Certification of plans etc.
  49. 42Service of notices
  50. 43Arbitration
  51. 44Procedure in relation to certain approvals etc. other than under Schedule 2
  52. 45Further provision as to approvals etc. under Schedule 2
  53. Signature
  54. Schedule 1AUTHORISED DEVELOPMENT
  55. Schedule 2: REQUIREMENTS
  56. Interpretation
  57. 1Paragraph 1
  58. In accordance with approved details
  59. 2Paragraph 2
  60. Construction Environmental Management Plan
  61. 3Paragraph 3
  62. Landscaping and habitat replacement
  63. 4Paragraph 4
  64. Implementation and maintenance of landscaping and habitat replacement
  65. 5Paragraph 5
  66. Highway works
  67. 6Paragraph 6
  68. 7Paragraph 7
  69. Alteration, reconstruction or replacement of buildings or bridges
  70. 8Paragraph 8
  71. Amendments to approved details
  72. 9Paragraph 9
  73. Schedule 3STREETS SUBJECT TO ALTERATION OF LAYOUT
  74. Schedule 4STREETS SUBJECT TO STREET WORKS
  75. Schedule 5STREETS TO BE STOPPED UP
  76. Schedule 6REPLACEMENT AND CLOSURE OF LEVEL CROSSING
  77. Schedule 7: LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED
  78. 1NETWORK RAIL
  79. 2NATIONAL GRID
  80. Schedule 8: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
  81. Compensation enactments
  82. 1Paragraph 1
  83. 2Paragraph 2
  84. Application of the 1965 Act
  85. 3Paragraph 3
  86. 4Paragraph 4
  87. 5Paragraph 5
  88. 6Paragraph 6
  89. 7Paragraph 7
  90. 8Paragraph 8
  91. 9Paragraph 9
  92. Schedule 9: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
  93. 1NETWORK RAIL
  94. 2NATIONAL GRID
  95. Schedule 10: PROTECTIVE PROVISIONS
  96. Part 1: PROTECTION FOR ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
  97. 1Paragraph 1
  98. 2Paragraph 2
  99. 3Paragraph 3
  100. 4Paragraph 4
  101. 5Paragraph 5
  102. 6Paragraph 6
  103. 7Paragraph 7
  104. 8Paragraph 8
  105. 9Paragraph 9
  106. 10Paragraph 10
  107. Part 2: PROTECTION FOR OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
  108. 11Paragraph 11
  109. 12Paragraph 12
  110. 13Paragraph 13
  111. 14Paragraph 14
  112. 15Paragraph 15
  113. Schedule 11PLANS AND DRAWINGS
  114. 1DESIGN DRAWINGS
  115. 2LAND PLANS
  116. 3STREET PLANS
  117. 4WORKS PLANS
  118. 5TRAFFIC REGULATION ORDER PLANS
  119. Schedule 12TRAFFIC REGULATION
  120. Explanatory note