The Network Rail (Norton Bridge Area Improvements) Order 2014
S.I. 2014/909 · Made 31 March 2014 · Extends to England, Wales and Scotland
Infrastructure Planning
Made 31st March 2014
Coming into force 21st April 2014
The application was examined in accordance with Chapter 4 of Part 6 of the 2008 Act, and the Infrastructure Planning (Examination Procedure) Rules 2010f3, by a single appointed person appointed by the Secretary of State in accordance with Chapter 3 of Part 6 of the 2008 Act.
The single appointed person, having considered the representations made and not withdrawn and the application together with accompanying documents, in accordance with section 83 of the 2008 Act, has submitted a report to the Secretary of State.
The Secretary of State, having considered the representations made and not withdrawn, and the report of the single appointed person, has decided to make an Order granting development consent for the development described in the application and consent for ancillary works with modifications which in the opinion of the Secretary of State do not make any substantial change to the proposals comprised in the application.
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and 122 of, and paragraphs 1 to 3, 10 to 17, 24, 26, 36 and 37 of Part 1 of Schedule 5 to, the 2008 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
-
S.I. 2009/2264, amended by S.I. 2010/439, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/722, S.I. 2013/755.
- f2
-
2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20).
- f3
Contents
- Part 1: Preliminary
- 1Citation and commencement
- 2Interpretation
- 3Incorporation of the Railways Clauses Acts
- Part 2: Principal Powers
- 4Development consent etc. granted by the Order
- 5Maintenance of authorised development
- 6Limits of deviation
- 7Benefit of Order
- Part 3: Streets
- 8Power to alter layout etc. of streets
- 9Street works
- 10Construction and maintenance of new or altered streets
- 11Stopping up of streets
- 12Application of the 1991 Act
- 13Temporary stopping up of streets
- 14Access to works
- 15Agreements with street authorities
- 16Construction of bridges and tunnels
- 17Level crossing
- Part 4: Supplemental powers
- 18Discharge of water
- 19Authority to survey and investigate the land
- Part 5: Powers of acquisition
- 20Compulsory acquisition of land
- 21Time limit for exercise of authority to acquire land compulsorily
- 22Compulsory acquisition of rights
- 23Private rights
- 24Application of the Compulsory Purchase (Vesting Declarations) Act 1981
- 25Acquisition of subsoil or airspace only
- 26Acquisition of part of certain properties
- 27Rights under or over streets
- 28Temporary use of land by Network Rail
- 29Temporary use of land by National Grid
- 30Temporary use of land for maintaining authorised development
- 31Statutory undertakers
- 32Apparatus and rights of statutory undertakers in stopped up streets
- 33Recovery of costs of new connections
- Part 6: Operations
- 34Operation and use of railways
- 35Felling or lopping of trees
- Part 7: Miscellaneous and general
- 36Operational land for purposes of the 1990 Act
- 37Defence to proceedings in respect of statutory nuisance
- 38Traffic regulation
- 39Protections of interests
- 40Application of the 1973 Act
- 41Certification of plans etc.
- 42Service of notices
- 43Arbitration
- 44Procedure in relation to certain approvals etc. other than under Schedule 2
- 45Further provision as to approvals etc. under Schedule 2
- Signature
- Schedule 1AUTHORISED DEVELOPMENT
- Schedule 2: REQUIREMENTS
- Interpretation
- 1Paragraph 1
- In accordance with approved details
- 2Paragraph 2
- Construction Environmental Management Plan
- 3Paragraph 3
- Landscaping and habitat replacement
- 4Paragraph 4
- Implementation and maintenance of landscaping and habitat replacement
- 5Paragraph 5
- Highway works
- 6Paragraph 6
- 7Paragraph 7
- Alteration, reconstruction or replacement of buildings or bridges
- 8Paragraph 8
- Amendments to approved details
- 9Paragraph 9
- Schedule 3STREETS SUBJECT TO ALTERATION OF LAYOUT
- Schedule 4STREETS SUBJECT TO STREET WORKS
- Schedule 5STREETS TO BE STOPPED UP
- Schedule 6REPLACEMENT AND CLOSURE OF LEVEL CROSSING
- Schedule 7: LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED
- 1NETWORK RAIL
- 2NATIONAL GRID
- Schedule 8: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
- Compensation enactments
- 1Paragraph 1
- 2Paragraph 2
- Application of the 1965 Act
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- Schedule 9: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
- 1NETWORK RAIL
- 2NATIONAL GRID
- Schedule 10: PROTECTIVE PROVISIONS
- Part 1: PROTECTION FOR ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- Part 2: PROTECTION FOR OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- Schedule 11PLANS AND DRAWINGS
- 1DESIGN DRAWINGS
- 2LAND PLANS
- 3STREET PLANS
- 4WORKS PLANS
- 5TRAFFIC REGULATION ORDER PLANS
- Schedule 12TRAFFIC REGULATION
- Explanatory note