Part 2 NATIONAL GRIDI1
England, Wales and Scotland
In the County of Staffordshire and the Borough of Stafford
(1) Number of land shown on land plans | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development |
|---|---|---|
| 1, 2, 3, 5, 7, 8, 11, 11a, 13, 19, 30, 30a, 37a, 42, 49, 50, 54, 55 | Worksites and access to works | Work Nos. 17, 18, 19A and 19B |
| 33, 34, 37, 38 | Construction and maintenance of pipe-line | Work No.17 |
| 34a (part) | Construction of pipe-line | Work No.17 |
| 52, 52a | Worksites and access to works | Work Nos. 17, 18, 19A and 19B |
| 56 | Construction of pipe-line | Work Nos. 18, 19A and 19B |
| 57 | Worksites and access to works | Work Nos. 18, 19A and 19B |
| 58, 59, 65, 67 | Construction of pipe-line | Work Nos. 19A and 19B |
| 61, 66, 77 | Worksites and access to works | Work Nos. 19A and 19B |
| 71 | Construction of pipe-line | Work No.19A |
| 76, 80, 87, 90, 96 | Worksites and access to works | Work Nos. 18, 19A and 19B |
Annotations
Commencement
- I1
Sch. 9 Pt. 2 in force at 21.4.2014, see art. 1