OpenLegislation

Article 4 Power to construct, etc., works

Original text. Later amendments are not shown.

(1)

Subject to the provisions of this Order, the Council may (within the lines and situations shown on the deposited plan and within the limit of deviation and according to the levels shown on the deposited sections) construct and maintain in the harbour—

  • Work No.1—a jetty of solid construction, protected on the seaward side by a rock armour of natural boulders, the outer edge of the wave wall of the jetty commencing at reference point 456310 East 077340 North on the Ventnor Esplanade, then extending by a curved line in a southerly direction to reference point 456385 East 077221 North and then returning by a curved line in a northerly direction and terminating in a new slipway connecting with the said Esplanade at reference point 456368 East 077343 North.

(2)

The Council may, within the limit of deviation, from time to time alter, enlarge, replace, relay, extend or reconstruct temporarily or permanently Work No.1.