Infrastructure Planning

Made 19th August 2025

Coming into force 20th August 2025

The Viking CCS Carbon Dioxide Pipeline Order 2025f1 (“the Viking CCS Pipeline Order”), which granted development consent within the meaning of the Planning Act 2008f2 (“the Act”) contains correctable errors within the meaning of paragraph 1 of Schedule 4 to the Act.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, before the end of the relevant period as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request from the applicantf3 for the correction of errors and omissions in the Viking CCS Pipeline Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed each relevant local planning authority for the area in which the land to which the Viking CCS Pipeline Order relates is situated that the request has been received.

The Secretary of State in exercise of the powers conferred by paragraphs 1(4) and (8) of Schedule 4 to, the Act, makes the following Order:

Annotations

Footnotes

f1

S.I. 2025/509.

f2

2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20). There are other amendments to the Act that are not relevant to this Order.

f3

The term “applicant” is defined in paragraph 4 of Schedule 4 to the Act.