The Viking CCS Carbon Dioxide Pipeline Order 2025
S.I. 2025/509 · Made 9 April 2025 · Extends to England and Wales
Infrastructure Planning
Made 9th April 2025
Coming into force 1st May 2025
The application was examined by a panel of three members appointed by the Secretary of State as Examining Authority (“the Panel”) in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f3.
The Panel, having considered the representations made and not withdrawn and the application together with the accompanying documents, has, in accordance with section 74(2)f4 of the 2008 Act, submitted a report and recommendation to the Secretary of State.
The Secretary of State has considered the representations made and not withdrawn, and the report and recommendation of the Panel, has taken into account the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017f5, and has had regard to the documents and matters referred to in section 105(2)f6 of the 2008 Act.
The Secretary of State is satisfied that common land and open space within the Order land, when burdened with any new rights authorised for compulsory acquisition under the terms of this Order, will be no less advantageous than it was before such acquisition, to the persons in whom it is vested, other persons, if any, entitled to rights of common or other rights, and the public, and that, accordingly, section 132(3) of the 2008 Act applies.
The Secretary of State is satisfied that common land within the Order land does not exceed 200 square metres in extent and the giving of other land in exchange for the order right is unnecessary, whether in the interests of the persons, if any, entitled to rights of common or other rights or in the interests of the public, and that, accordingly, section 132(5) of the 2008 Act applies.
The Secretary of State, having decided the application, has determined to make an Order granting development consent for the development described in the application with modifications which in the opinion of the Secretary of State do not make any substantial changes to the proposals comprised in the application.
The Secretary of State, in exercise of the powers conferred by sections 114f7, 115f8, 117f9, 120f10, 122f11, 123f12 and 132f13 of the 2008 Act, makes the following Order—
Annotations to the whole text
Footnotes
- f1
-
2008 c. 29. Section 37 was amended by section 137(5) of, and paragraph 5 of Schedule 13 to, the Localism Act 2011 (c. 20).
- f2
- f3
- f4
-
Section 74(2) was amended by paragraph 29 of Schedule 13 to the Localism Act 2011 (c. 20).
- f5
- f6
-
Section 105(2) was amended by paragraph 50 of Schedule 13 to the Localism Act 2011.
- f7
-
Section 114 was amended by paragraph 55 of Schedule 13 to the Localism Act 2011.
- f8
-
Section 115 was amended by section 160 of the Housing and Planning Act 2016 (c. 22) and section 43 of the Wales Act 2017 (c. 4).
- f9
-
Section 117 was amended by paragraph 58 of Schedule 13 and paragraph 1 of Schedule 25 to the Localism Act 2011.
- f10
-
Section 120 was amended by section 140 of, and paragraph 60 of Schedule 13 to, the Localism Act 2011.
- f11
-
Section 122 was amended by paragraph 62 of Schedule 13 to the Localism Act 2011.
- f12
-
Ibid.
- f13
-
Section 132 was amended by section 24 of the Growth and Infrastructure Act 2013 (c. 27).
Contents
- Part 1: Preliminary
- 1Citation and commencement
- 2Interpretation
- Part 2: Principal Powers
- 3Development consent etc. granted by the Order
- 4Operation and use of the authorised development
- 5Power to maintain the authorised development
- 6Limits of deviation
- 7Benefit of the Order
- Part 3: Streets
- 8Application of the permit scheme
- 9Street works
- 10Power to alter layout, etc. of streets
- 11Application of the 1991 Act
- 12Temporary restriction of public rights of way
- 13Temporary restriction of use of streets
- 14Access to works
- 15Agreements with street authorities
- 16Use of private roads
- 17Traffic regulation
- Part 4: Supplemental powers
- 18Discharge of water
- 19Maintenance of drainage works
- 20Authority to survey and investigate the land
- 21Protective work to buildings
- Part 5: Powers of Acquisition
- 22Compulsory acquisition of land
- 23Time limit for exercise of authority to acquire land compulsorily
- 24Compulsory acquisition of rights and restrictive covenants
- 25Statutory authority to override easements and other rights
- 26Compulsory acquisition of land: minerals
- 27Private rights
- 28Application of the 1981 Act
- 29Acquisition of subsoil or airspace only
- 30Modification of Part 1 of the 1965 Act
- 31Rights under or over streets
- 32Temporary use of land for carrying out the authorised development
- 33Temporary use of land for maintaining the authorised development
- 34Statutory undertakers
- 35Recovery of costs of new connections
- Part 6: Miscellaneous and general
- 36Application and modification of legislative provisions
- 37Defence to proceedings in respect of statutory nuisance
- 38Application of landlord and tenant law
- 39Felling or lopping of trees and removal of hedgerows
- 40Trees subject to Tree Preservation Orders
- 41Crown rights
- 42Protective provisions
- 43Planning legislation
- 44Certification of plans, etc.
- 45Service of notices
- 46No double recovery
- 47Requirements, appeals, etc.
- 48Arbitration
- Signature
- Schedule 1
- 1Authorised development
- Part 2: Ancillary works
- 1Paragraph 1
- Schedule 2: Requirements
- Part 1: Requirements
- 1Interpretation
- 2Time limits
- 3Stages of authorised development
- 4Scheme design
- 5Construction environmental management plan
- 6Construction traffic
- 7Highway accesses
- 8Surface water drainage
- 9Contaminated land and groundwater
- 10Archaeology
- 11Landscape and ecological management plan
- 12Ecological surveys
- 13Construction hours
- 14Restoration of land
- 15Operational phase mitigation plan
- 16Decommissioning environmental management plan
- 17Donna Nook Air Weapon Range
- 18Written approval
- 19Amendments to approved details
- 20Offshore consents
- 21Biodiversity net gain
- 22Anticipatory steps towards compliance with any requirement
- Part 2: Procedure for discharge of Requirements
- 23Applications made under requirements
- 24Multiple discharging authorities
- 25Further information
- 26Fees
- 27Appeals
- 28Outcome of appeals
- 29Interpretation
- Schedule 3: Streets subject to street works
- 1Streets subject to permanent street works
- 2Streets subject to temporary street works
- Schedule 4: New means of access
- 1New permanent means of access from the public highway
- 2New temporary means of access from the public highway
- Schedule 5Public rights of way to be temporarily restricted
- Schedule 6Land of which only temporary possession may be taken
- Schedule 7Land in which only new rights etc., may be acquired
- Schedule 8: Modification of compensation and compulsory purchase enactments for creation of new rights
- 1Compensation enactments
- 2Compensation enactments
- 3Compensation enactments
- 4Application of Part 1 of the 1965 Act
- Schedule 9: Protective provisions
- Part 1: Protection for electricity, gas, water and sewerage undertakers
- 1Paragraph 1
- 2Paragraph 2
- 3On street apparatus and offshore works
- 4Acquisition of land
- 5Removal of apparatus
- 6Facilities and rights for alternative apparatus
- 7Retained apparatus
- 8Expenses and costs
- 9Expenses and costs
- 10Miscellaneous
- Part 2: Protection for operators of electronic communications code networks
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- Part 3: For the protection of National Grid Electricity Transmission plc as electricity undertaker
- 15Application
- 16Interpretation
- 17On Street Apparatus
- 18Apparatus of statutory undertakers in temporarily restricted streets
- 19Protective works to buildings
- 20Acquisition of land
- 21Removal of apparatus
- 22Facilities and rights for alternative apparatus
- 23Retained apparatus: protection of electricity undertaker
- 24Expenses
- 25Indemnity
- 26Enactments and agreements
- 27Co-operation
- 28Access
- 29Arbitration
- 30Notices
- Part 4: For the protection of National Gas Transmission plc as gas undertaker
- 31Application
- 32Interpretation
- 33On Street Apparatus
- 34Apparatus of National Gas in stopped up streets
- 35Protective works to buildings
- 36Acquisition of land
- 37Removal of apparatus
- 38Facilities and rights for alternative apparatus
- 39Retained apparatus: protection
- 40Expenses
- 41Indemnity
- 42Enactments and agreements
- 43Co-operation
- 44Access
- 45Arbitration
- 46Notices
- Part 5: For the protection of Cadent Gas Limited
- 47Application
- 48Interpretation
- 49On Street apparatus
- 50Apparatus of Cadent in stopped up streets
- 51Protective works to buildings
- 52Acquisition of land
- 53Removal of apparatus
- 54Facilities and rights for alternative apparatus
- 55Retained apparatus: protection of Cadent
- 56Expenses
- 57Indemnity
- 58Enactments and agreements
- 59Co-operation
- 60Access
- 61Arbitration
- 62Notices
- Part 6: For protection of Railway Interests
- 63Paragraph 63
- 64Paragraph 64
- 65Paragraph 65
- 66Paragraph 66
- 67Paragraph 67
- 68Paragraph 68
- 69Paragraph 69
- 70Paragraph 70
- 71Paragraph 71
- 72Paragraph 72
- 73Paragraph 73
- 74Paragraph 74
- 75Paragraph 75
- 76Paragraph 76
- 77Paragraph 77
- 78Paragraph 78
- 79Paragraph 79
- 80Paragraph 80
- 81Paragraph 81
- 82Paragraph 82
- 83Paragraph 83
- 84Paragraph 84
- Part 7: For the protection of the Environment Agency
- 85Paragraph 85
- 86Submission and approval of plans
- 87Construction of protective works
- 88Timing of works and service of notices
- 89Works not in accordance with this Schedule
- 90Maintenance of works
- 91Remediating impaired drainage work
- 92Agency access
- 93Free passage of fish
- 94Indemnity
- 95Indemnity
- 96Disputes
- Part 8: For the protection of Northern Powergrid (Yorkshire) Plc
- 97Paragraph 97
- 98Paragraph 98
- 99Paragraph 99
- 100Paragraph 100
- 101Paragraph 101
- 102Paragraph 102
- 103Paragraph 103
- 104Paragraph 104
- 105Paragraph 105
- 106Paragraph 106
- 107Paragraph 107
- 108Paragraph 108
- 109Paragraph 109
- 110Paragraph 110
- 111Paragraph 111
- 112Paragraph 112
- 113Paragraph 113
- Part 9: For the protection of National Highways Limited
- 114Application etc.
- 115Interpretation
- 116General
- 117Prior approvals
- 118Construction of the specified works
- 119Payments
- 120Completion of a specified work
- 121Security
- 122Insurance
- 123Indemnity
- 124Maintenance of the specified works
- 125Land
- 126Expert Determination
- 127Co-operation
- Part 10: For the protection of Anglian Water
- 128Application
- 129Interpretation
- 130On street apparatus
- 131Apparatus in stopped up streets
- 132Protective works to buildings
- 133Acquisition of land
- 134Removal of apparatus
- 135Facilities and rights for alternative apparatus
- 136Retained apparatus
- 137Expenses and costs
- 138Indemnity
- 139Cooperation
- 140Cooperation
- 141Cooperation
- Part 11: For the protection of Phillips 66 Limited
- 142Application
- 143Interpretation
- 144Authorisation of works details affecting pipelines or protected crossings
- 145Authorisation of works details affecting pipelines or protected crossings
- 146Authorisation of works details affecting pipelines or protected crossings
- 147Authorisation of works details affecting pipelines or protected crossings
- 148Notice of works
- 149Further provisions about works
- 150Monitoring for damage to pipelines
- 151Monitoring for damage to pipelines
- 152Compliance with requirements etc applying to the protected land
- 153Restriction on exercising powers
- 154Insurance
- 155Costs
- 156Indemnity
- 157Further protection in relation to the exercise of powers under the Order
- 158Further protection in relation to the exercise of powers under the Order
- 159Further protection in relation to the exercise of powers under the Order
- 160Expert Determination
- 161Notices
- Part 12: For the protection of Immingham Oil Terminal operators
- 162Application
- 163Interpretation
- 164Acquisition of apparatus
- 165Authorisation of works details affecting pipelines or protected crossings
- 166Authorisation of works details affecting pipelines or protected crossings
- 167Authorisation of works details affecting pipelines or protected crossings
- 168Authorisation of works details affecting pipelines or protected crossings
- 169Notice of works
- 170Monitoring for damage to pipelines
- 171Monitoring for damage to pipelines
- 172Monitoring for damage to pipelines
- 173Costs
- 174Indemnity and other provisions
- 175Further protection in relation to the exercise of powers under the Order
- 176Further protection in relation to the exercise of powers under the Order
- 177Further protection in relation to the exercise of powers under the Order
- 178Expert Determination
- 179Notices
- Part 13: For the protection of Air Products (BR) Limited
- 180Application
- 181Interpretation
- 182Acquisition of land
- 183Removal of apparatus
- 184Facilities and rights for alternative apparatus
- 185Authorisation of works details affecting pipelines or protected crossings
- 186Authorisation of works details affecting pipelines or protected crossings
- 187Authorisation of works details affecting pipelines or protected crossings
- 188Notice of works
- 189Carrying out work and monitoring for damage to pipelines
- 190Carrying out work and monitoring for damage to pipelines
- 191Carrying out work and monitoring for damage to pipelines
- 192Costs
- 193Indemnity
- 194Expert Determination
- 195Notices
- Part 14: FOR THE PROTECTION OF UNIPER UK LIMITED
- 196Paragraph 196
- 197Paragraph 197
- 198Paragraph 198
- 199Apparatus of Uniper in temporarily closed, altered or diverted streets
- 200Protective works to buildings
- 201Acquisition of land
- 202Retained apparatus
- 203Removal or replacement of apparatus
- 204Expenses
- 205Indemnity
- 206Co-operation
- 207Access
- 208Confidentiality
- 209Arbitration
- 210Notices
- Schedule 10: Arbitration rules
- 1Primary objective
- 2Time periods
- 3Timetable
- 4Procedure
- 5Arbitrator’s powers
- 6Costs
- 7Confidentiality
- Explanatory note