Paragraph 166 Authorisation of works details affecting pipelines or protected crossingsI1

England and Wales

No part of a relevant work is to be commenced until one of the following conditions has been satisfied—

(a)

the works details supplied in respect of that relevant work under paragraph ‎165 have been approved by the IOT Operators; or

(b)

the works details supplied in respect of that relevant work under paragraph ‎165 have been authorised by an expert under paragraph ‎168.

Annotations

Commencement

I1

Sch. 9 para. 166 in force at 1.5.2025, see art. 1(2)