Paragraph 166 Authorisation of works details affecting pipelines or protected crossingsI1
England and Wales
No part of a relevant work is to be commenced until one of the following conditions has been satisfied—
(a)
the works details supplied in respect of that relevant work under paragraph 165 have been approved by the IOT Operators; or
(b)
the works details supplied in respect of that relevant work under paragraph 165 have been authorised by an expert under paragraph 168.
Annotations
Commencement
- I1
Sch. 9 para. 166 in force at 1.5.2025, see art. 1(2)