Article 4 Operation and use of the authorised developmentI1
England and Wales
(1)
The undertaker may at any time operate and use the authorised development and the existing pipeline except to the extent that this Order or an agreement made under this Order provides otherwise.
(2)
Subject to the provisions of this Order the undertaker is granted consent to use the existing pipeline for the conveyance of carbon dioxide.
(3)
The consent granted under paragraphs (1) and (2) does not relieve the undertaker from compliance with any obligation under the Pipeline Safety Regulations 1996f1.
Annotations
Commencement
- I1
Art. 4 in force at 1.5.2025, see art. 1(2)
Footnotes
- f1