Paragraph 10 Seasonal restrictions in respect of fish spawningI1

England and Wales

(1)

The undertaker must ensure that no percussive piling activity takes place during the cod spawning period from 15th February to 31st March (inclusive) of any year.

(2)

The undertaker must ensure that no percussive piling activity takes place during the herring spawning period from 15th September to 15th November (inclusive) for any year, within such areas as agreed with the MMO prior to the commencement of construction. The undertaker must provide to the MMO the results of noise modelling prepared to an agreed methodology to inform the selection of such areas.

Annotations

Commencement

I1

Sch. 9 Pt. 2 para. 10 in force at 28.11.2014, see art. 1