OpenLegislation

Regulation 19 Adjustment of non-core spending obligation: scheme years 13 to 15I1

England and Wales

(1)

The adjustments that must be made to the non-core spending obligation for a scheme year (other than scheme year 12) (“O”) of a compulsory scheme electricity supplier (“C”) are as follows.

(2)

O must be adjusted in accordance with paragraph (3) or (4) if I is less than or exceeds S where—

(a)

“I” is the amount of spending incurred by C under this Part (as determined by the Authority in accordance with regulation 27) in the preceding scheme year;

(b)

“S” is C’s non-core spending obligation for the preceding scheme year as adjusted for that year, where required, in accordance with regulation 18 or this regulation.

(3)

If I is less than S, O must be adjusted by adding (S − I).

(4)

If I exceeds S, O must be adjusted by subtracting the lesser of—

(a)

(I − S), and

(b)

the relevant amount.

(5)

For the purposes of paragraph (4) “the relevant amount” is—

(a)

5% of S, or

(b)

where C notified the Authority of their intention to meet all or part of a failed supplier’s non-core spending obligation in accordance with regulation 29, 10% of S.

(6)

Whether or not an adjustment is made under paragraph (2), O must be adjusted by adding an amount equal to the undelivered rebate amount.

(7)

For the purposes of paragraph (6) “the undelivered rebate amount” is £150 multiplied by, where C has made a notification under regulation 12(8) in respect of the preceding scheme year, the number of prescribed rebates as stated in that notification.

Annotations

Commencement

I1

Reg. 19 in force at 7.7.2022, see reg. 1(2)