OpenLegislation

Regulation 17 Adjustment of non-core spending obligation: scheme year 12I1

England, Wales and Scotland

(1)

The adjustments that must be made to the non-core spending obligation for scheme year 12 (“O”) of a compulsory scheme electricity supplier (“C”) are as follows.

(2)

O must be adjusted in accordance with paragraph (3) or (4) if I is less than or exceeds S where—

(a)

“I” is the amount of spending incurred by C under Part 4 of the 2011 Regulations in scheme year 11 (as determined by the Authority in accordance with regulation 29(1)(d) of those Regulations);

(b)

“S” is C’s non-core spending obligation under that Part of those Regulations for scheme year 11, as adjusted (where required) in accordance with regulation 14 of those Regulations.

(3)

If I is less than S, O must be adjusted by adding an amount equal to 9.4% of (S - I).

(4)

If I exceeds S, O must be adjusted by subtracting the lesser of—

(a)

an amount equal to 9.4% of (I - S); and

(b)

an amount equal to 9.4% of the overspend amount.

(5)

For the purposes of paragraph (4) “the overspend amount” is—

(a)

5% of S; or

(b)

where C notified the Authority of their intention to meet all or part of a failed supplier’s non-core spending obligation in accordance with regulation 30A of the 2011 Regulations in scheme year 11, 10% of S.

(6)

Whether or not an adjustment is made under paragraph (2), O must be adjusted by adding an amount equal to 9.4% of the undelivered rebate amount.

(7)

For the purposes of paragraph (6) “the undelivered rebate amount” is £140 multiplied by—

(a)

where C has made a notification under regulation 9(7) of the 2011 Regulations in respect of scheme year 11, the number of prescribed rebates as stated in that notification; and

(b)

where C has made a notification under regulation 14(3A) of the 2011 Regulations in respect of scheme year 11, the number of prescribed rebates as stated in that notification.

Annotations

Commencement

I1

Reg. 17 in force at 20.10.2022, see reg. 1(2)