Section 24A Abstraction licencesF1
Each licence to abstract water shall be of one of the following three types—
a licence to abstract water from one source of supply over a period of twenty-eight days or more for any purpose (a “full licence”);
a licence to abstract water from one source of supply over a period of twenty-eight days or more for the purpose of—
transferring water to another source of supply; or
transferring water to the same source of supply, but at another point, in the course of dewatering activities in connection with mining, quarrying, engineering, building or other operations (whether underground or on the surface),
in either case without intervening use (a “transfer licence”);
a licence to abstract water from one source of supply over a period of less than twenty-eight days (a “temporary licence”).
In this Act, a reference (however expressed) to a licence to abstract water is to be taken as a reference to all types of licence, unless it is clear that a different meaning is intended.
Annotations
Textual amendments
- F1
S. 24A inserted (1.4.2006) by Water Act 2003 (c. 37), ss. 1(1), 105(3); S.I. 2006/984, art. 2(a) (with Sch. paras. 1, 2)
Notes on Part II
Modifications
- C1
Pt. II: transfer of functions to the Environment Agency (1.4.1996) by 1995 c. 25, s. 2(1)(a)(i) (with ss. 115, 117); S.I. 1996/186, art. 3
Notes on Chapter II
Modifications
- C1
Chapter II of Part II excluded (1.4.1996) by 1995 c. 25, s. 6(3) (with ss. 7(6), 115, 117); S.I. 1996/186, art. 3
- C2
Chapter II of Part II modified (18.12.1996) by 1996 c. 61, s. 52, Sch. 15 Pt. III para. 11
- C3
Pt. II Ch. II modified (22.3.2005) by Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), Sch. 11 para. 11 (with art. 51)
- C4
Pt. II Ch. II modified (26.8.2005) by River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), art. 1, Sch. 10 para. 14 (with arts. 45(1), 48, Sch. 10 paras. 21, 29)
- C5
Pt. II Ch. II modified (19.3.2007) by Ouseburn Barrage Order 2007 (S.I. 2007/608), art. 1, Sch. 6 para. 18 (with arts. 46-48, Sch. 6 paras. 17(5), 23)
- C6
Pt. II Ch. II modified (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 17 para. 11
- C7
Pt. II Ch. II modified (9.6.2009) by Nottingham Express Transit System Order 2009 (S.I. 2009/1300), arts. 1, 71(12) (with Sch. 13 para. 14(2), Sch. 14 para. 19, Sch. 16)
- C8
Pt. II Ch. II modified (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), art. 1, Sch. 11 para. 12
- C9
Pt. II Ch. II modified (27.8.2010) by The Llangollen and Corwen Railway Order 2010 (S.I. 2010/2136), art. 1(1), Sch. 4 para. 12
- C10
Pt. II Ch. II modified (1.9.2010) by The Port of Bristol (Deep Sea Container Terminal) Harbour Revision Order 2010 (S.I. 2010/2020), art. 1(2), Sch. 6 para. 11(1) (with arts. 18, 19)
- C11
Pt. II Ch. II modified (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), art. 1, Sch. 10 para. 41(1) (with art. 51, Sch. 10 paras. 6885)