Section 42 Consideration of called-in applications.C1

England and Wales

(1)

Subject to the following provisions of this section and to section 46 below, the Secretary of State, on considering a called-in application—

(a)

may determine that a licence shall be granted containing such provisions as he considers appropriate; or

(b)

if, having regard to the provisions of this Act, he considers it necessary or expedient to do so, may determine that no licence shall be granted.

(2)

Before determining a called-in application, the Secretary of State may, if he thinks fit-

(a)

cause a local inquiry to be held; or

(b)

afford to the applicant and the F1appropriate agency an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for the purpose;

and the Secretary of State shall act as mentioned in paragraph (a) or (b) above if a request is made by the applicant or the appropriate agency to be heard with respect to the application.

(3)

The provisions of sections 37, 38(1) and (3), 39(2) and 40 above shall apply in relation to any called-in application as if—

(a)

any reference in those provisions to the appropriate agency, except the references in sections F237 and 38(3)(a), were a reference to the Secretary of State; and

(b)

any reference to section 39(1) above were a reference to subsection (4) below.

(4)

F3Subject to subsection (4A) below, in determining any called-in application and, in particular, in determining what (if any) direction to give under subsection (5) below, the Secretary of State shall consider whether any such direction would require the grant of a licence which would so authorise—

(a)

the abstraction of water; or

(b)

the flow of any inland waters to be obstructed or impeded by means of impounding works,

as to derogate from rights which, at the time when the direction in question is given, are protected rights for the purposes of this Chapter.

F4(4A)

Subsection (1A) of section 39 above applies in relation to subsection (4) above as it applies in relation to section 39(1) above.

(5)

Where the decision of the Secretary of State on a called-in application is that a licence is to be granted, the decision shall include a direction to the appropriate agency to grant a licence containing such provisions as may be specified in the direction.

(6)

The decision of the Secretary of State on any called-in application shall be final.

(7)

In this section “called-in application” means an application referred to the Secretary of State in accordance with directions under section 41 above.

Annotations

Textual amendments

F1

Words in ss. 33A-45 substituted (1.4.2013) by The Natural Resources Body for Wales (Functions) Order 2013 (S.I. 2013/755), art. 1(2), Sch. 2 para. 270(g) (with Sch. 7)

F2

Word in s. 42(3)(a) substituted (1.4.2006) by Water Act 2003 (c. 37), ss. 14(3)(b), 105(3); S.I. 2006/984, art. 2(i) (with Sch. paras. 1, 2)

F3

Words in s. 42(4) inserted (1.4.2004) by Water Act 2003 (c. 37), ss. 16(6)(a), 105(3); S.I. 2004/641, art. 3(e) (with Sch. 3 para. 7)

F4

S. 42(4A) inserted (1.4.2004) by Water Act 2003 (c. 37), ss. 16(6)(b), 105(3); S.I. 2004/641, art. 3(e) (with Sch. 3 para. 7)

Modifications

C1

S. 42 applied (with modifications) (1.4.2006) by Water Resources (Abstraction and Impounding) Regulations 2006 (S.I. 2006/641), reg. 1(2), Sch. 2 para. 7

Notes on Part II

Modifications

C1

Pt. II: transfer of functions to the Environment Agency (1.4.1996) by 1995 c. 25, s. 2(1)(a)(i) (with ss. 115, 117); S.I. 1996/186, art. 3

Notes on Chapter II

Modifications

C1

Chapter II of Part II excluded (1.4.1996) by 1995 c. 25, s. 6(3) (with ss. 7(6), 115, 117); S.I. 1996/186, art. 3

C2

Chapter II of Part II modified (18.12.1996) by 1996 c. 61, s. 52, Sch. 15 Pt. III para. 11

C3

Pt. II Ch. II modified (22.3.2005) by Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), Sch. 11 para. 11 (with art. 51)

C4

Pt. II Ch. II modified (26.8.2005) by River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), art. 1, Sch. 10 para. 14 (with arts. 45(1), 48, Sch. 10 paras. 21, 29)

C5

Pt. II Ch. II modified (19.3.2007) by Ouseburn Barrage Order 2007 (S.I. 2007/608), art. 1, Sch. 6 para. 18 (with arts. 46-48, Sch. 6 paras. 17(5), 23)

C6

Pt. II Ch. II modified (22.7.2008) by Crossrail Act 2008 (c. 18), Sch. 17 para. 11

C7

Pt. II Ch. II modified (9.6.2009) by Nottingham Express Transit System Order 2009 (S.I. 2009/1300), arts. 1, 71(12) (with Sch. 13 para. 14(2), Sch. 14 para. 19, Sch. 16)

C8

Pt. II Ch. II modified (20.7.2010) by The Network Rail (Nuneaton North Chord) Order 2010 (S.I. 2010/1721), art. 1, Sch. 11 para. 12

C9

Pt. II Ch. II modified (27.8.2010) by The Llangollen and Corwen Railway Order 2010 (S.I. 2010/2136), art. 1(1), Sch. 4 para. 12

C10

Pt. II Ch. II modified (1.9.2010) by The Port of Bristol (Deep Sea Container Terminal) Harbour Revision Order 2010 (S.I. 2010/2020), art. 1(2), Sch. 6 para. 11(1) (with arts. 18, 19)

C11

Pt. II Ch. II modified (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), art. 1, Sch. 10 para. 41(1) (with art. 51, Sch. 10 paras. 6885)