Regulation 3 ApplicationF1I1

Northern Ireland

(1)

An environmental impact assessment shall be carried out in accordance with these Regulations in relation to a relevant project.

(2)

A project is a relevant project if –

(a)

it is a water management project for agriculture, including an irrigation project; and

(b)

it would be likely to have significant effects on the environment by virtue, inter alia, of its nature, size or location.

(3)

A project is not a relevant project if it –

(a)

constitutes development to which the Planning (Environmental Impact Assessment) Regulations (Northern Ireland) 1999f1 apply;

(b)

constitutes the carrying out of drainage works within the meaning of the Drainage (Environmental Impact Assessment) Regulations (Northern Ireland) 2001f2; or

(c)

involves the abstraction, diversion or impoundment of less than 200 cubic metres of water in any period of 24 hours.

Annotations

Textual amendments

F1

Regulations revoked with savings (5.6.2017) by The Water Resources (Environmental Impact Assessment) Regulations (Northern Ireland) 2017 (S.R. 2017/85), regs. 1, 13(1)(a) (with reg. 13(2))

Commencement

I1

Reg. 3 in operation at 9.3.2005, see reg. 1

Footnotes

f1

S.R. 1999 No. 73

f2

S.R. 2001 No. 394