Regulation 5 NotificationI1
Northern Ireland
Subject to paragraph (2), any person who proposes to install a water fitting in connection with any of the operations listed in the Table below—
shall give notice to the water undertaker that he proposes to begin work;
shall not begin that work without the consent of the water undertaker which shall not be withheld unreasonably; and
shall comply with any conditions to which the water undertaker’s consent is subject.
| Table |
|---|
|
This regulation does not apply to the installation by an approved contractor of a water fitting falling within paragraph 2, 4(b), 4(l) or 4(m) in the Table.
The notice required by paragraph (1) shall include or be accompanied by—
the name and address of the person giving the notice, and (if different) the name and address of the person on whom notice may be served under paragraph (4);
a description of the proposed work or material change of use; and
particulars of the location of the premises to which the proposal relates, and the use or intended use of those premises;
except in the case of a fitting falling within paragraph 4(a), (c), (h) or 5 in the table—
a plan of those parts of the premises to which the proposal relates, and
a diagram showing the pipework and fitting to be installed; and
where the work is to be carried out by an approved contractor, the name of the contractor.
The water undertaker may withhold consent required under paragraph (1), or grant it subject to conditions, by a notice given before the expiry of the period of ten working days commencing with the day on which notice under that paragraph was given.
If no notice is given by the water undertaker within the period mentioned in paragraph (4), the consent required under paragraph (1) shall be deemed to have been granted unconditionally.