Paragraph 12 I1
Northern Ireland
The water system shall be capable of withstanding an internal water pressure not less than 1½ times the maximum pressure to which the installation or relevant part is designed to be subjected in operation ( “the test pressure”).
This requirement shall be deemed to be satisfied—
in the case of a water system that does not include a pipe made of plastics, where—
the whole system is subjected to the test pressure by pumping, after which the test continues for one hour without further pumping;
the pressure in the system is maintained for one hour; and
there is no visible leakage throughout the test;
in any other case, where either of the following tests is satisfied—
| TEST A | TEST B |
|---|---|
|
|
Annotations
Commencement
- I1
Sch. 2 para. 12 in operation at 3.8.2009, see reg. 1(1)