OpenLegislation

Regulation 25 Authorisations: terms and conditions

(1)

Subject to paragraph (2), a departure may be authorised under regulation 24 for such period as is in the Department's opinion reasonably required for securing a supply of water for regulation 5(1) purposes that fully satisfies the requirements of Part 3 (“the departure period”).

(2)

No departure period may exceed three years.

(3)

Subject to paragraph (4), an authorisation under regulation 24—

(a)

must specify—

(i)

the grounds on which it is granted;

(ii)

every water supply zone in respect of which it is granted;

(iii)

the extent to which a departure from the prescribed concentration or value of any parameter is authorised;

(iv)

in respect of each parameter to which paragraph (iii) applies, the results of the analysis of the samples taken in each water supply zone in question during the 12 months immediately preceding the first day on which the prescribed concentration or value could not be met;

(v)

in respect of each parameter to which paragraph (iii) applies, the results of the analysis of the samples (if any) taken in each water supply zone in question between the first day on which the prescribed concentration or value could not be met and the date of the application;

(vi)

the average daily quantity of water supplied from each of those zones or, if that quantity cannot readily be ascertained, the average daily quantity of water supplied from the treatment works that supplies water to that zone;

(vii)

the estimated population of each of those zones;

(viii)

whether or not any relevant food-production undertaking would be affected; and

(ix)

the departure period; and

(b)

must require the implementation of a scheme for monitoring the quality of water supplied in each of those zones during the departure period (which may be, but need not be, the scheme submitted in accordance with regulation 24(3)(b)); and

(c)

must require the carrying out of the steps which, in its opinion, are reasonably required in order to secure that the supply fully satisfies the requirements of Part 3 (whether or not the steps are those proposed in the summary submitted in accordance with regulation 24(3)(c)); and

(d)

must specify, in relation to those steps—

(i)

the timetable for the work;

(ii)

an estimate of the cost of the work; and

(iii)

provisions for reviewing the progress of the work and for reporting to it the result of the review;

(e)

must require the taking of such steps as may be specified to give to the population within the water supply zones to which the authorisation applies and, in particular, to those groups of that population for which the supply of water in accordance with the authorisation could present a special risk, advice as to the measures (if any) that it would be advisable in the interests of their health for persons within that population or those groups to take for the whole or any part of the departure period.

(4)

Where the Department is of the opinion—

(a)

that the extent of the contravention of requirements of Part 3 as respects any parameter is trivial; and

(b)

that the prescribed concentration or value as respects that parameter is likely to be achieved within the period of 30 days beginning with the day on which the prescribed concentration or value in respect of that parameter was contravened,

the particulars to be specified in the authorisation must be those required by paragraph (3)(a) (iii) and (ix), and sub-paragraphs (b) to (d) of that paragraph shall not apply.

(5)

Where it appears to the Department that a supply of water that fully satisfies the requirements of Part 3 cannot be restored by the end of the departure period, it may authorise a F1further two departures.

(6)

Paragraphs (1) to (5) shall apply to a further departure as they apply to a departure authorised under regulation 24.

F2(7)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(8)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Annotations

Textual amendments

F1

Words in reg. 25(5) substituted (31.12.2020) by The Water (Amendment) (Northern Ireland) (EU Exit) Regulations 2019 (S.I. 2019/112), regs. 1(1), 14(5)(a); 2020 c. 1, Sch. 5 para. 1(1)

F2

Reg. 25(7)(8) omitted (31.12.2020) by virtue of The Water (Amendment) (Northern Ireland) (EU Exit) Regulations 2019 (S.I. 2019/112), regs. 1(1), 14(5)(b); 2020 c. 1, Sch. 5 para. 1(1)