Made 25th October 2023

Coming into force 26th October 2023

An application has been made under paragraph 2 of Schedule 6 to the Planning Act 2008f1 to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011f2 for a non-material change to the West Midlands Rail Freight Interchange Order 2020f3.

The Secretary of State, having considered the application and the responses to the publicity and consultation carried out in accordance with regulations 6 and 7 of the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011, has decided to make this Order amending the West Midlands Rail Freight Interchange Order 2020.

The Secretary of State, in exercise of the powers conferred by paragraph 2 of Schedule 6 to the Planning Act 2008, makes the following Order—

Annotations to the whole text

Footnotes

f1

2008 c. 29. Paragraph 2 of Schedule 6 was amended by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23), by paragraph 72 of Schedule 13 and paragraph 1 of Schedule 25 to the Localism Act 2011 (c. 20) and by section 28 of the Infrastructure Act 2015 (c. 7).

f2

S.I. 2011/2055, as amended by S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/755, S.I. 2015/377, S.I. 2015/760, S.I. 2015/1682, S.I. 2017/314, S.I. 2017/524, S.I. 2018/378, S.I. 2019/734, S.I. 2020/764 and S.I. 2020/1534.

f3

S.I. 2020/511 amended by S.I. 2020/1163.

Contents

  1. 1Citation and commencement
  2. 2Amendment of the West Midlands Rail Freight Interchange Order 2020
  3. Signature
  4. Schedule: CERTIFICATION DOCUMENTS
  5. 1Paragraph 1
  6. Explanatory note

1Citation and commencement

This Order may be cited as the West Midlands Rail Freight Interchange (Amendment) Order 2023 and comes into force on 26th October 2023.

2Amendment of the West Midlands Rail Freight Interchange Order 2020

(1)

The West Midlands Rail Freight Interchange Order 2020 is amended as follows.

(2)

In article 4 (parameters of authorised development)—

(a)

at the end of sub-paragraph (a) insert “and in respect of new onsite road infrastructure (comprised in Work Nos. 4, 5, 7 and 10) deviate vertically from the levels shown on the parameters plans to the extent stated in the note to those plans”; and

(b)

for sub-paragraph (b) substitute—

“(b)

in respect of bridges—

(i)

deviate vertically from the levels shown highlighted yellow on the bridge plans to a maximum of 0.5 metres upwards or 1.0 metres downwards; and

(ii)

deviate laterally from the position of the bridge abutments shown on the bridge plans to the maximum extent described and shown highlighted blue on the bridge plans; and”.

(3)

For the table in Schedule 15 (certification documents) substitute the table shown in the Schedule.

Signature

Signed by authority of the Secretary of State for Transport

Gareth Leigh

Head of Transport and Works Act Orders Unit

Department for Transport

25th October 2023

1

Documents for certification that they are true copies of the documents referred to in this Order

(1)

Document/Plan

(2)

Document Number

(3)

Document date/Plan number with revision number

Access and rights of way plans
Key plan2.3WSP-70001979-SK-060 Rev I
Sheet 12.3AWSP-70001979-SK-060 Rev H
Sheet 22.3BWSP-70001979-SK-060 Rev G
Sheet 32.3CWSP-70001979-SK-060 Rev F
Sheet 42.3DWSP-70001979-SK-060 Rev F
Sheet 52.3EWSP-70001979-SK-060 Rev F
Sheet 62.3FWSP-70001979-SK-060 Rev F
Sheet 72.3GWSP-70001979-SK-060 Rev B
The book of reference4.3B21 August 2019
The bridge plans
Proposed road bridges plan and long section2.18A1516-0425-WDK-SI-C-301-010 Rev P11
Road Bridge B12.18B1516-0425-WDK-SI-C-301-006 Rev P14
Road Bridge B2 and B32.18C1516-0425-WDK-SI-C-300-007 Rev P14
Proposed road bridge B4 section and elevation2.18D1516-0425-WDK-SI-C-301-008 Rev P17
The design and access statement7.53 August 2018
The environmental statement6.2

3 August 2018 (subject to the substitutions set out below):

(i) Figures 10.001, 10.002, 10.003 and 10.004 – 12 September 2018

(ii) Annex 10.1.1 – 12 September 2018

(iii) Addendum to Chapter 13 (Noise and Vibration) – 5 April 2019

(iv) Appendix I to Transport Assessment (Appendix 15.1) (Site Wide HGV Management Plan) – 7 May 2019

(v) Appendix H to Transport Assessment (Appendix 15.1) (Site Wide Travel plan) – 5 July 2019

(vi) Appendix 2.3 (Outline Demolition and Construction Management Plan) – 5 July 2019

(vii) Appendix 10.4 (Framework Ecological Mitigation and Management Plan) – 5 July 2019

(viii) Updated Chapter 7 (Air Quality) and Appendices 7.2, 7.3, 7.4, 7.6 and 7.7 – 7 August 2019

The future highways maintenance plans
Key Plan2.10WSP-70001979-SK-091 Rev F
Sheet 12.10AWSP-70001979-SK-091 Rev F
Sheet 22.10BWSP-70001979-SK-091 Rev C
Sheet 32.10CWSP-70001979-SK-091 Rev C
The highway classification plans
Key Plan2.13WSP-70001979-SK-068 Rev I
Sheet 12.13AWSP-70001979-SK-068 Rev H
Sheet 22.13BWSP-70001979-SK-068 Rev E
Sheet 32.13CWSP-70001979-SK-068 Rev E
The highway general arrangement plans
Key Plan/Highway Masterplan2.9WSP-70001979-GA-100 Rev M
General Arrangement Plan 1012.9AWSP-70001979-GA-101 Rev E
General Arrangement Plan 1022.9BWSP-70001979-GA-102 Rev E
General Arrangement Plan 1032.9CWSP-70001979-GA-103 Rev I
General Arrangement Plan 1042.9DWSP-70001979-GA-104 Rev M
General Arrangement Plan 1052.9EWSP-70001979-GA-105 Rev E
General Arrangement Plan 1062.9FWSP-70001979-GA-106 Rev G
General Arrangement Plan 1072.9GWSP-70001979-GA-107 Rev H
General Arrangement Plan 1082.9HWSP-70001979-GA-108 Rev F
General Arrangement Plan 1092.9IWSP-70001979-GA-109 Rev G
General Arrangement Plan 1102.9JWSP-70001979-GA-110 Rev H
General Arrangement Plan 1112.9KWSP-70001979-GA-111 Rev H
The land plans
Key Plan2.1Key Plan v1
Sheet 12.1ASheet 1 of 12 v0
Sheet 22.1BSheet 2 of 12 v0
Sheet 32.1CSheet 3 of 12 v0
Sheet 42.1DSheet 4 of 12 v1
Sheet 52.1ESheet 5 of 12 v0
Sheet 62.1FSheet 6 of 12 v0
Sheet 72.1GSheet 7 of 12 v0
Sheet 82.1HSheet 8 of 12 v0
Sheet 92.1ISheet 9 of 12 v0
Sheet 102.1JSheet 10 of 12 v0
Sheet 112.1KSheet 11 of 12 v0
Sheet 122.1LSheet 12 of 12 v0
Order limits plan2.44990-00011 Rev 06
The parameters plans
Development Zone Parameters Plan
Key Plan2.54990-02000 Rev 08
Sheet 12.5A4990-02001 Rev 08
Sheet 22.5B4990-02002 Rev 08
Sheet 32.5C4990-02003 Rev 09
Sheet 42.5D4990-02004 Rev 07
Floor Levels and Building Heights Parameters Plan
Key Plan2.64990-02010 Rev 08
Sheet 12.6A4990-02011 Rev 07
Sheet 22.6B4990-02012 Rev 07
Sheet 32.6C4990-02013 Rev 08
Sheet 42.6D4990-02014 Rev 07
Green Infrastructure Parameters Plan
Key Plan2.74990-02020 Rev 11
Sheet 12.7A4990-02021 Rev 10
Sheet 22.7B4990-02022 Rev 10
Sheet 32.7C4990-02023 Rev 11
Sheet 42.7D4990-02024 Rev 09
The illustrative arrangement of railway alignment2.14TRS-DRG-FA-001003 Rev 05
The rail terminal – illustrative expanded rail terminal layout plan2.15BTRS-DRG-FA-001010 Rev 04
The rail section plans
Rail Alignment Cross Sections – Sheet 12.16ATRS-DRG-FA-001005 Rev 02
Rail Alignment Cross Sections – Sheet 22.16BTRS-DRG-FA-001006 Rev 03
Rail Alignment Cross Sections – Sheet 32.16CTRS-DRG-FA-001007 Rev 02
Long sections rail alignment Sheet 12.16DTRS-DRG-FA-001004 Rev 02
Long sections rail alignment Sheet 22.16ETRS-DRG-FA-001008 Rev 02
The speed limit plans
Key Plan2.12WSP-70001979-SK-062 Rev I
Sheet 12.12AWSP-70001979-SK-062 Rev K
Sheet 22.12BWSP-70001979-SK-062 Rev F
Sheet 32.12CWSP-70001979-SK-062 Rev E
SI facility plan2.2001
The traffic regulation plans
Key Plan2.11WSP-70001979-SK-061 Rev I
Sheet 12.11AWSP-70001979-SK-061 Rev H
Sheet 22.11BWSP-70001979-SK-061 Rev E
Sheet 32.11CWSP-70001979-SK-061 Rev F
Sheet 42.11DWSP-70001979-SK-061 Rev A
The works plans
Key Plan2.2Key Plan v3.0
Sheet 12.2ASheet 1 of 9 v3.0
Sheet 22.2BSheet 2 of 9 v3.0
Sheet 32.2CSheet 3 of 9 v1
Sheet 42.2DSheet 4 of 9 v1
Sheet 52.2ESheet 5 of 9 v1
Sheet 62.2FSheet 6 of 9 v3.0
Sheet 72.2GSheet 7 of 9 v1
Sheet 82.2HSheet 8 of 9 v1
Sheet 92.2ISheet 9 of 9 v1

Explanatory note

(This note is not part of the Order)

This Order amends the West Midlands Rail Freight Interchange Order 2020 (S.I. 2020/511) (“the 2020 Order”), a development consent order under the Planning Act 2008 (“the Act”).

This Order follows an application under paragraph 2 of Schedule 6 to the Act to make the following non-material changes to the 2020 Order—

(a)

the parameters of the authorised development in article 4(a) are amended to provide for vertical deviation in respect of the new onsite road infrastructure from the levels shown and described on the parameters plans;

(b)

the parameters of the authorised development in article 4(b) are amended to provide for lateral deviation from the position of the bridge abutments shown on the bridge plans to the maximum extent shown highlighted blue on the bridge plans;

(c)

the table in Schedule 15 is substituted with the table shown in the Schedule to provide an updated list of the certified documents that relate to the 2020 Order as amended by this Order.

A copy of the substituted plans mentioned in this Order may be inspected free of charge during working hours at the offices of South Staffordshire Council at Wolverhampton Road, Codsall, Wolverhampton, WV8 1PX.