Paragraph 18 Landscape – phasing of landscaping and ecology works
The undertaker must complete the landscaping works identified in column (2) of the following table by no later than the stage of the authorised development set out in column (3) of that table or such alternative later triggers as are agreed by the local planning authority.
| (1) Item as identified on the green infrastructure parameters plan | (2) Description | (3) Stage of Authorised Development |
|---|---|---|
| (i) | Croft Lane Community Park | To be completed within 5 years of the commencement of the authorised development. |
| (ii) | The ecological corridor linking Calf Heath Wood and Calf Heath Reservoir | To be completed within 5 years of the commencement of the authorised development, or prior to commencement of development at Development Zones A4a or A4b as shown on the green infrastructure parameters plan, whichever is sooner. |
| (iii) | The southern section of Calf Heath Community Park | To be completed prior to the commencement of development at Development Zones A4b as shown on the green infrastructure parameters plan. |