Paragraph 38 Rail Support
The undertaker must appoint a rail freight co-ordinator at least 3 months prior to the submission of the application for approval of GRIP 3 referred to in paragraph (1) of requirement 40 (rail provision milestones) who must report to the local planning authority no less than once a quarter on—
the progress towards meeting the rail provision milestones;
the progress of the rail terminal works; and
the operation of the rail terminal when open including—
the appointment of a rail operator to operate the rail terminal;
the amount of rail freight usage of the rail terminal;
the number of trains using the rail terminal;
the warehousing receiving or sending goods through the rail terminal; and
the amount of goods being received or sent through the rail terminal by freight handlers not occupying the warehousing.