Paragraph 3 Notice of commissioning

Original text. Later amendments are not shown.

(1)

Notice of commencement of commissioning of Work No 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is commenced.

(2)

Notice of completion of commissioning of Work No 1 must be given to the relevant planning authority within 7 days of the date on which commissioning is completed.