OpenLegislation

Paragraph 14 Trans-Pennine Ethylene PipeI1

England and Wales

No soil stripping operations may be carried out until the precise route of the Trans‑Pennine ethylene pipeline adjacent to the south western site boundary has been identified. The south western perimeter bund must be located a minimum of 10m from the route of the pipeline and the south western boundary of the landfill must be located a minimum of 28m from the route of the pipeline. The route of the pipeline together with the standoffs must be clearly identified with markers prior to the commencement of the authorised project.

Annotations

Commencement

I1

Sch. 2 para. 14 in force at 9.6.2015, see art. 1