Schedule 8 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKENI1
England, Wales and Scotland
| (1) | (2) | (3) |
|---|---|---|
| Area | Number of land shown on land plans | Purpose for which temporary possession may be taken |
| East Staffordshire and South Derbyshire | All plots described in the book of reference and shown on the land plans excluding plots prefixed with ‘S’ and excluding the plot numbered 115 | Carrying out the authorised development granted by this Order and shown on the works plans sheets 1 to 10, including fencing, vegetation clearance, ecological mitigation work (where necessary), topsoil stripping, hedgerow removal, construction of access facilities, taking of access, excavation of shafts and tunnels, pipeline construction work, constructing temporary bridges and culverts, constructing micro-tunnels and shafts, constructing temporary compounds, reinstatement and marking and any other works required for the carrying out of the authorised development. |
Annotations
Commencement
- I1
Sch. 8 in force at 7.1.2015, see art. 1