OpenLegislation

Paragraph 2 I1

England, Wales and Scotland

In this Part—

  • “construction” includes execution, placing, alteration and reconstruction, and “construct” and “constructed” have corresponding meanings;

  • “engineer” means an engineer appointed by Canal & River Trust and approved by the undertaker for the purposes of this Order;

  • “Canal & River Trust” means the Canal & River Trust acting as a trustee of the Waterways Infrastructure Trust or any successor body performing the same functions which holds any waterways within the works limits;

  • “code of practice” means the code of practice for works affecting British waterways (April 2010) as amended from time to time;

  • “plans” includes sections, designs, design data, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction), programmes and details of the extent, timing and duration of any proposed use or occupation of any Canal & River Trust property;

  • “specified work” means so much of any of the authorised development to be situated upon, across, under, over or within the waterway or that may in any way adversely affect the waterway;

  • “Canal & River Trust property” means any land owned by Canal & River Trust within the works limits and includes land covered with water, sub-soil, air space and waterways;

  • “1940 Conveyance rights” means such rights as may be enjoyed by Canal & River Trust over plot 119 (as shown on the land plans) pursuant to a conveyance dated 23rd May 1940 as detailed in registered title number DY 160721;

  • “waterway” means the canal within the works limits and includes any pond or other waterway or course situated on Canal & River Trust property, any works, services, apparatus, equipment, lands (including subsoil) or premises belonging to or under the control of Canal & River Trust and held or used by it in connection with its statutory functions.

Annotations

Commencement

I1

Sch. 9 Pt. 4 para. 2 in force at 7.1.2015, see art. 1