Paragraph 11 Construction hoursI1
England, Wales and Scotland
(1)
Construction work for the authorised development must not take place outside the hours of—
(a)
07:00 to 19:00 on Monday to Friday; and
(b)
07:00 to 13:00 on Saturdays and public holidays.
(2)
(3)
Nothing in sub-paragraph (1) precludes a start-up period from 06:30 to 07:00 and a shut-down period from 19:00 to 19:30 on weekdays (excluding public holidays) and a start-up period from 06:30 to 07:00 and a shut-down period from 13:00 to 13:30 on Saturdays and public holidays.