To prevent any movement of BT apparatus within or immediately adjacent to the Order land during any excavation as part of the construction of the authorised development, structural support is to be used as directed by Click Before You Dig or the Network Alteration team if the excavation is—

(a)

deeper than the immediately adjacent BT apparatus;

(b)

within 1 metre of BT apparatus in stable soil; or

(c)

within 5 metres of BT apparatus in unstable soil.