Paragraph 20 I1

England and Wales

(1)

The plans and construction methodology submitted for approval under paragraph 7 of this Part of this Schedule must have regard to the principles set out in the relevant constructability notes but a refusal of plans or construction methodology from a protected asset owner from whom approval is sought under paragraph 7 is not to be deemed to be unreasonable solely on the basis that the plans and construction methodology comply with the relevant constructability note.

(2)

The minimum headroom clearance between the upper surface of the hot metal rail and bridge shown as MC3 on the conveyor route plans and the underside of the conveyor must be 7.850 metres.

(3)

The minimum headroom clearance between the upper surface of the road and bridge shown as MC6 on the conveyor route plans and the underside of the conveyor must be 8.240 metres.