Paragraph 12 Obstruction in riverI1
England and Wales
If any pile, stump or other obstruction to navigation becomes exposed in the course of constructing any tidal work (other than a pile, stump or other obstruction on the site of a structure comprised in any permanent work), the undertaker, as soon as reasonably practicable after the receipt of notice in writing from the Tees Port Authority requiring such action, must remove it from the river or, if it is not reasonably practicable to remove it—
cut the obstruction off at such level below the bed of the river as the Tees Port Authority may reasonably direct; or
take such other steps to make the obstruction safe as the Tees Port Authority may reasonably require.
Annotations
Commencement
- I1
Sch. 11 para. 12 in force at 10.8.2016, see art. 1