Paragraph 7 Construction Traffic Management PlanI1

England and Wales

None of the authorised development is to commence (excluding ecological mitigation or enhancement works referred to in the outline ecological management plan) until a Construction Traffic Management Plan (“CTMP”) drafted in accordance with the principles set out in Appendix 12.3 of the environmental statement has been submitted to and approved by the local planning authority. The provisions of the approved CTMP must be observed at all times during the construction of the authorised development.

Annotations

Commencement

I1

Sch. 2 para. 7 in force at 10.8.2016, see art. 1